Another Tool in the Tool Box for The Tunneling Company

Jun 18, 2023

In the world of trenchless construction, there are only three guarantees; the specified pipe tends to be larger, the drive lengths tend to get longer and installation must be completed precisely. The Tunneling Company (TTC) has always been innovative and eager to accept the most challenging projects. Over the years, TTC has continually invested in the latest technology and innovatively found ways to successfully complete the projects that others said can't be done.

A few years ago, TTC recognized the potential of using hydraulically powered pipe ramming hammers horizontally. These hammers were traditionally used in a vertical manner on some of the world's largest pile driving projects. Hydraulic hammers have been used in some horizontal applications over the last 10 to 15 years but because of the complicated and challenging setup, the idea never really caught on with the exception of a few key projects. TTC's in-house innovation changed all of that.

As with many great concepts, the idea was originally drafted up on a napkin. The idea was to place the hydraulic hammer in our own patented hydraulic jacking frame which the concept was born between Shawn Gaunt, Malcolm Bachand and Rich Bachand, all original partners in TTC. The idea quickly expanded into a digital mock-up and then fabricated in-house into a working model which quickly proved itself in the field time after time. Some have called it a "game changer" when it comes to larger diameter steel pipe installation in a variety of soil types. At a minimum, it is another "tool in our tool box," says Gaunt, The Tunneling Company's president.

Most recently, TTC recognized the opportunity to use this ‘tool’ to install surface casings or conductor barrels for horizontal directional drilling (HDD). Surface casings are required when incompetent ground is present which could result in a break in circulation of the drilling fluid casing a frac-out. HDD designers are now designing challenging HDDs to incorporate surface casing to reduce the risk of a frac-out and to navigate through unconsolidated formations. As with many trenchless designs these days, surface casing tends to require larger diameters and longer drive lengths. It wasn't long ago that a surface casing of 30m (98ft) x 900mm (36") was considered a big surface casing project. Today, surface casings are being designed with a final diameter of up to 2.13 m (84") and a final depth of up to 100 m (328ft). With the power and efficiency of the hydraulic hammer, these designs are achievable. These installations are not without challenges but the hydraulic hammer has proven its effectiveness.

The new challenge is once the casing has been successfully installed and the HDD has been completed, how does one extract the casing to minimize the corrosion potential on the product pipe and minimize any additional environmental impact by leaving the casing in the ground? Once again, the management team at TTC needed an innovative way to successfully extract these very large surface casings. Traditionally, a pneumatic (air) hammer was called on to extract these casings as it had been effective and efficient in the past based on smaller diameters and shorter drive lengths. However, an air hammer doesn't produce nearly the drive energies of a hydraulic hammer so once a casing had been installed with the hydraulic hammer, extraction efforts with an air hammer were proving to be futile. This time around, Elliott Brown – Operations Manager, was heavily involved in the brainstorming sessions as he brought with him extensive experience with the hydraulic hammer and the hands-on challenges with extraction efforts with an air hammer. The ideas and challenges generated from these discussions were drafted up into a digital design but were not put forward until the right project came along.

TTC did not have to wait long for that right project as there have been a number of large diameter HDDs designed and installed over the last year that required extensive casing installations. TTC was contacted to see if they had the means and methods to extract 68m (223ft) of 1.8m (72"). Extraction efforts had already been made with one of the world's largest pneumatic hammers which proved unsuccessful. Leaving the casing in the ground was not an option and time was of the essence. TTC knew the hydraulic hammer had the energy required to remove this casing, the challenge was the extraction harness concept was not fully designed and had not yet been fabricated or proven. As TTC has done so many times in the past, they accepted the challenge and got to work. The design was revised and completed specifically for this casing diameter, the installed length and the anticipated energy required to extract this casing. A final design was completed days later and the in-house fabrication team got to work. Fabrication ran 24/7 for about a week until the working model was complete. Some tests and minor alterations were completed in the yard prior to mobilization to the job site where the real test would take place.

Upon arrival of the equipment, the crews had already completed any necessary preparation work on the casing and around the job site, which included digging down and cutting off 24m of casing to help reduce some of the weight of the casing that needed to be safely managed. The equipment was unloaded, prepared for extraction, and welded into place on the casing. After two shifts to properly prep everything for extraction, the moment of truth. The hammer was turned on and slowly warmed up to 35kJ of the potential 90kJ available on this hammer which got the pipe moving. No signs of failure were noted so the hammer was turned up to 42kJ and then 48kJ for the next couple of hours. At this energy output, the pipe started moving at a rate of 3m per hour. After the initial two hours or extraction, the pipe started to really pick up and extraction rates of 5m per hour. By 4:30 of that day, extraction was successfully complete. The efforts of the crew and equipment exceed TCC's expectation and the client could not have been happier with the final outcome.

The hydraulic hammer extraction equipment has found a permanent home in TTC's tool box alongside their pneumatic hammers, auger boring machines, guided boring machines, horizontal down the hole pneumatic rock hammers, small boring unit rock cutters and microtunneling equipment. These, in addition to The Crossing Company's complete line of horizontal directional drills including several 1.2 million pound maxi-rigs, allows the group of companies to be a true one stop shop for all trenchless construction needs throughout Canada and the USA.

For more information, please visit www.crossinggroup.com.

Nick Hyde is project manager at The Tunneling Company.